Reference
·Primary source
Hyperscaler combined Thailand commitment
~USD 7B+
Combined announced infrastructure commitments: AWS USD 5B over 15 years (Jan 2025), Google Cloud USD 1B+ (May 2024), Microsoft USD 1B+ (Q4 2024). Excludes follow-on phases.
Figure in context
Combined announced infrastructure commitments: AWS USD 5B over 15 years (Jan 2025), Google Cloud USD 1B+ (May 2024), Microsoft USD 1B+ (Q4 2024). Excludes follow-on phases.
Combined announced infrastructure commitments: AWS USD 5B over 15 years (Jan 2025), Google Cloud USD 1B+ (May 2024), Microsoft USD 1B+ (Q4 2024). Excludes follow-on phases.
Time scope
2024-2025 announcements
Source basis
Primary source
Interpretation notes
What this tells you
Combined announced infrastructure commitments: AWS USD 5B over 15 years (Jan 2025), Google Cloud USD 1B+ (May 2024), Microsoft USD 1B+ (Q4 2024). Excludes follow-on phases.
What not to do with it
Use the linked report for interpretation and keep basis differences explicit.
Related figures
Adjacent numbers that add context without drowning the value.
Thailand datacenter operating IT load (2024 baseline)
Structure Research, operator disclosures
Thailand datacenter operating IT load (2027 base case)
Structure Research, operator phasing, BOI Section 8 pipeline
Hyperscale data centre capex per MW IT load (Thailand 2026)
Operator filings, EPC tender summaries
New build PUE target band (Bangkok hyperscale 2026-27)
Operator sustainability disclosures, MDES certifications
GPU-as-a-service share of Thai AI workload (2027 modelled)
Operator disclosures, NVIDIA AI Center Thailand, hyperscaler partner channel data
BoT virtual banking licence winners with GPU-cluster commitments
Bank of Thailand virtual bank licence press, winners' disclosures
Report context
Atlas actors in this figure's reports
Profiles covered in the report that cite this number.